Golden Valley Electric Association
July 16, 1998
Table of Contents
Introduction
GVEA's Response to APUC Order R-98-2
Other Matters

Corporate Computing
Corporate & Operational Communications
SCADA Operations and Security
Pipeline Operations
Fairbanks Area Generation Plants
Healy Generation Plant
Transmission and Distribution Facilities
Building Facilites and Fire Protection

Via Facsimile and Overnight Mail

Alaska Public Utilities Commission
Attention: Records and Filing
1016 West Sixth Avenue, Suite 400
Anchorage, AK 99501


  Re: Golden Valley Electric Association, Inc. - APUC Certificate # 13
    Response to R-98-2 (1); Commission Investigation Into Readiness of
    Public Utilities and Pipeline Carriers To Provide Service in the New     Millennium



Dear Commission:

  Golden Valley Electric Association, Inc., submits the following response to the Commission's Order in Docket R-98-2 regarding the status of Year 2000 compliance efforts of public utilities and pipeline carriers.

I. INTRODUCTION

  GVEA is an electrical cooperative association that provides electric service to its members in Alaska's Northern interior. GVEA currently serves over 30,000 meter locations, operates and maintains over 2,000 miles of transmission and distribution lines, and is interconnected to the Railbelt utility grid. As the enclosed information will demonstrate, GVEA is involved in significant efforts to insure its electric system and members experience a smooth transition into the new millennium. Based on information available at this time, GVEA believes it's equipment and systems may be at risk of diminished functuality or failure due to Year 2000 issues. Such diminuation of functuality and/or system failures could precipitate a wide range of problems ranging from minor inconveniences to outages. In order to minimize the risk of Year 2000 issues, GVEA is preparing a comprehensive planning document, GVEA's Year 2000 Planning Document (Plan).
  GVEA has a target date of the 3rd Quarter of 1998 for all critical systems to be in the final phase of testing. By the end of the 2nd quarter of 1999, all equipment and systems should be returned to service and Year 2000 compliant. At this time, GVEA does not anticipate any Year 2000-related problems in providing service to its members before and beyond January 1, 2000. It is our goal to make the switch-over transparent to our customers.
  GVEA is finalizing its Plan to assist employees in managing the issues involved in the assessment, revision and testing of all of GVEA's critical systems. The Plan will be forwarded to the attention of the Commission when available.


II. GVEA'S RESPONSE TO APUC ORDER R-98-2 (1)

  The following is GVEA's response to the specific inquiries that were included in the Commission's June 16, 1998, Order in R-98-2.


1. Provide the following information about your Year 2000 Project Leader(s).

GVEA's Year 2000 Project Leaders are:

Brad Evans
Telephone: 907/451-5655
E-mail: bwevans@gvea.com
Fax: 907/451-0556
Jeff Yauney
Telephone: 907/458-5778
E-mail: jpyauney@gvea.com
Fax: 907/451-5650


2. Do you have a Year 2000 planning document?

Yes. As noted earlier, GVEA is in the process of finalizing its Plan. GVEA management intends to distribute the Plan among its employees as an additional tool for identifying any and all systems that may be affected by Year 2000 issues. By having all employees informed of the Year 2000 issues (through distribution of the Plan, newsletters and normal internal communications), GVEA expects to have a full awareness of all systems that may be at risk. It is expected that this information exchange will encourage employees involved with systems that may have been overlooked in the Plan to bring those areas to the attention of management.


  If yes,please include a copy with this response.


The Plan will be forwarded to the attention of the Commission when available.

  Where are you in this planning cycle?

GVEA has identified eight areas of Year 2000 responsibility internal to its organization.

  1) Corporate Computing
  2) Corporate and Operational Communications
  3) SCADA Operations and Security
  4) Pipeline Operations
  5) Fairbanks Area Generation Plants
  6) Healy Generation Plant
  7) Transmission and Distribution Facilities
  8) Building Facilities and Fire Protection


The Project Team Members, individuals responsible for each of these areas, are listed below along with a summary of the planning cycle status of each area.


1) Corporate Computing

Project Team Member
Name: Jeff Yauney
Phone:
(907)458-5778
e-mail:
jpyauney@gvea.com
Fax:
(907)451-5650

Planning Status
* Launch
* Inventory
* Assessment

* Repair

* Testing

* Finished



Completed.
Completed.
In progress, with some systems completed.
In progress, with some systems completed.
In progress, with some systems completed.
In progress, with some systems completed.


2) Corporate and Operational Communications

Project Team Member
Name: Jeff Yauney
Phone:
   (907)458-5778
e-mail:
   jpyauney@gvea.com
Fax:
   (907)451-5650

Planning Status
* Launch
* Inventory
* Assessment

* Repair

* Testing

* Finished

Completed.
Completed.
In progress, with some systems completed.
In progress, with some systems completed.
In progress, with some systems completed.
In progress, with some systems completed.


3) SCADA Operations and Security

Project Team Member
Name: Fred LeBeau
Phone:
   (907)451-5640
e-mail:
   falebeau@gvea.com
Fax:
   (907)451-0556

Planning Status
* Launch
* Inventory
* Assessment
* Repair
* Testing
* Finished

Completed.
Completed.
Completed.
In progress.
In progress.
Pending.


4) Pipeline Operations

Project Team Member
Name: Alex Gajdos
Phone:
   (907)451-5654
e-mail:
  asgajdos@gvea.com
Fax:
   (907)451-5682

Planning Status
* Launch
* Inventory
* Assessment
* Repair

* Testing
* Finished

Completed.
Completed.
Completed.
In progress waiting on final from vendor.
Pending.
Pending.


5) Fairbanks Area Generation Plants

Project Team Member
Name: Alex Gajdos
Phone:
   (907)451-5654
e-mail:
   asgajdos@gvea.com
Fax:
   (907)451-5682

Planning Status
* Launch
* Inventory
* Assessment
* Repair

* Testing
* Finished

Completed.
Completed.
Completed.
In progress waiting on final from vendor.
Pending.
Pending.


6) Healy Generation Plant

Project Team Member
Name: Frank Abegg
Phone:
   (907)451-5659
e-mail:
   fabegg@gvea.com
Fax:
   (907)451-5682

Planning Status
* Launch
* Inventory
* Assessment
* Repair
* Testing
* Finished

Begun.
In progress.
Pending.
Pending.
Pending.
Pending.


7) Transmission and Distribution Facilities

Project Team Member
Name: Tim Devries
Phone:
   (907)451-5669
e-mail:
   trdevries@gvea.com
Fax:
   (907)451-5638

Planning Status
* Launch
* Inventory
* Assessment

* Repair
* Testing
* Finished

Completed.
Completed.
Partially complete, waiting on vender response.
Pending assessment.
Pending.
Pending.


8) Building Facilities and Fire Protection

Project Team Member
Name: Tom Hartnell
Phone:
   (907)451-5663
e-mail:
   tkhartnell@gvea.com
Fax:
   (907)451-5681

Name: Dave Gardner
Phone:
   (907)451-5635
e-mail:
   dgardner@gvea.com
Fax
(907)451-5619
Planning Status
* Launch
* Inventory
* Assessment
* Repair
* Testing
* Finished

Completed.
Completed.
Completed.
Completed.
Completed.
Completed.

Project Team Members are responsible for taking five basic steps for their areas of responsibility.


STEP 1: Conduct a physical inventory to identify equipment and systems using date-related hardware or software.

Project team members are responsible for compiling an inventory list of all software, hardware, embedded systems or overall systems that are subject to Year 2000 risks in their area of responsibility. Corporate systems provided company wide will be addressed by area of responsibility (not where the device or system physically may reside).

The entire project team will compile a unique company wide list of equipment and systems at risk as a result as a result of Year 2000 issues. This list will be widely distributed within GVEA. Feedback will be encouraged.

STEP 2: Assess software, hardware and systems for Year 2000 compliance.

Each project team member will assess their area of responsibility and determine if equipment and or systems are Year 2000 compliant. Correspondence from vendors certifying compliance is required to complete assessment when such information is available and can be obtained. Each system or piece of equipment will be classified in one of the following five categories:

  Class 1 Critical to system operations; may result in electrical outages, interruption of pipeline operations, loss of fuel delivery, fire hazard or safety, loss of security, loss of communications, loss of essential corporate network functions utilized in operations and loss of essential building controls.

  Class 2 Critical to administrative functions but will not cause interruptions to electrical service or create a safety problem.

  Class 3 Critical to system operations but manual override of automatic systems defeats the Year 2000 issues.

  Class 4 May cause equipment or system to stop operating but equipment or system is not critical.

  Class 5 May cause equipment or system to merely report the wrong date but functionality is not effected.

In the interest of reliability and preservation of resources, these classifications will be utilized to prioritize Project Team Members work plans. Classes 1, 2 and 3 will receive the most attention and resources. All equipment and systems are subject to being reclassified if their output effects downstream functionality of a critical piece of equipment or system.

STEP 3: Modify/replace non-compliant equipment or systems.

Each Project Team Member will be responsible for coordinating conversion or replacement of non-compliant equipment and/or systems. For each system, plans will be submitted to the entire project team outlining the actions to be taken. The Project Team Leaders will monitor progress and assist where needed. Monthly department reports will include progress made in each area of responsibility. The Project Team Leaders will be responsible for reporting the progress of the entire group. A progress report and reference document will be maintained by each Project Team Member and submitted to the Project Team Leaders on a quarterly basis.

STEP 4: Test equipment/systems affected by Step 3.

All equipment and systems that are time sensitive and subject to Year 2000 issues, will be tested. All systems will be tested from "end to end" to satisfactorily pass the intent of Step 5). All testing will consider the effects of any software or system, which may be effected before the actual date of January 1, 2000. Systems and or software may have look forward subroutines, which can effect functionality before reaching the end of the year. Tests are intended to be complete and must be performed.

Testing plans will be submitted to the project team and review for compliance. Factory or vendor tests must be documented and submitted with a testing plan if testing takes place off site.

STEP 5: Placing modified/replaced systems and hardware into service.

Modified, upgraded or replaced equipment and systems must be continually monitored for performance. This step will be the final review of successful migration to the year 2000 before the event actually occurs.


3. What actions remain to be taken by your company in order for your software to be fully Year-2000 compliant?

The general progress GVEA has made to date varies by area. GVEA has made the greatest progress in the areas of: Corporate Computing, Pipeline Operations, SCADA Operations and Security, Fairbanks Area Generation Plants and Building Facilities and Fire Protection. The review of the Building Facilities and Fire Protection area is complete. The SCADA Operations and Security and Corporate Computing areas are in testing. Numerous other systems are awaiting vendor modifications and/or upgrades to make the systems Year 2000 compliant. Work on some systems is on hold pending vendor verification of Year 2000 compliance.

GVEA's response to the specific inquiries are included in the attached compilations made by the Project Team Leaders responsible for the identified area.

4.What actions remain to be taken for your computer hardware to be fully Year-2000 compliant?

See attached.

5. What actions remain to be taken for your utility or pipeline facilities to be fully Year-2000 compliant?

See attached.

6. What actions remain to be taken in order for your infrastructure to be fully Year-2000 compliant?

See attached.

7. What actions have you taken to identify and test embedded chips within your infrastructure?

See attached.

8. What specific Year-2000 problems have you found and in what way could they affect the services you provide?

See attached.

9. Summarize the resources you anticipate will be necessary for your company to remedy your Year-2000 issues.

See attached.

10. What facilities and equipment have vendors certified as Year-2000 compliant?

See attached.

11. Provide any comments or advice what may be helpful in addressing this issue.

See attached.

12. Are new purchases required in order for your company to be Year-2000 compliant?

See attached.

13. Are you working with any trade organization for Year-2000 compliance assistance? If yes, please identify.

See attached.

14. What entities outside your organization are you dependent on, and what actions are you taking to ensure that the services provided by the external system are not affected by the Year-2000 issue?

See attached.


III. OTHER MATTERS

External systems and services important to GVEA operations will be investigated on a parallel path to our own internal program. We have identified the external systems/services critical to our electric system operations to be: the North Pole Refinery, Alyeska Pipeline operations, North Slope fuel production, State of Alaska micro-wave communications, leased communications services of any form, Bradley Lake Hydroelectric Project (and related transmission facilit1ies), other electric utility operations and Cook Inlet gas production and delivery. GVEA intends to address Railbelt inter-utility issues through the Alaska Intertie Operating Committee. Other non-electric utility systems/services will be addressed on a case-by-case basis with the relevant governing body or service provider.

A final measure for external systems and service review will be for GVEA to determine whether the Plan should consider the interruption of any external services critical to GVEA's operations. The necessity of including such a review in the Plan would increase if critical external systems are believed not to be Year 2000 compliant or the risk of failure is too great to have compliance left to chance.

Unfortunately, the Plan is not expected to address consumer systems that may fail for Year 2000 issues. GVEA would like to extend our services and help individual consumers, however our own systems are most critical and this problem has stretched our resources to their utmost limits.

        Respectfully submitted this 16th day of July, 1998.


        ___________________________________________________
        Ronald L. Saxton
        Kirk H. Gibson
        ATER WYNNE LLP
        222 SW Columbia, Suite 1800
        Portland, Oregon 97201-6618
        phone: 503/226-1191
        503/226-0079

        Attorneys for Golden Valley Electric Association, Inc.


Attached Information


Section 1: Corporate Computing

Team Leader
Jeff Yauney
phone: (907) 458-5778
e-mail: jpyauney@gvea.com
fax: (907) 451-5650

Introduction

This section outlines the time-line and tasks necessary to assure Y2000 compliance for all administrative systems, programs, application/file servers, desktop applications within Golden Valley?s Corporate Computing Environment. All computers, operating systems and software applications will be certified by June 1999. Certification will be achieved using one or more of the following methods:
        Obtain certification from suppliers for compliant products
        Perform remedial action on systems with known non-compliance
        Perform extensive testing using actual data/time rollover on modified systems

Item 2: Year 2000 planning cycle status for Corporate Computing

*Launch
*Inventory
*Assessment
*Repair
*Testing
*Finished
Completed.
Completed.
Completed.
In progress, with some systems already completed.
In progress, with some systems already completed.
In progress, with some systems already completed.


Item 3: Actions remaining for corporate software to be Y2000 compliant.

Administrative Systems and Programs In 1997, Golden Valley completed a review of utility software packages and selected Orcom Systems, Inc., to replace the existing administrative systems. The Orcom software is Y2000 compliant, and will be installed by the summer of 1999.

With the installation of any new system there is the possibility of unforeseen problems that can directly affect the projected installation time-line. With this in mind, Golden Valley completed a formal review of the existing administrative systems and associated hardware platforms for Y2000 compliance.


Existing Administrative Systems & Programs The review of the existing administrative systems found that the bulk of the VAX based, COBOL programs were not Y2000 compliant. Upon completion of this phase, a complete list of programming time estimates was compiled, followed by a concerted effort to bring the largest program area, the billing system, into Y2000 compliance. With the Y2000 modifications to the billing system complete, the original estimates for the remaining systems and programs were reworked. Utilizing the experience gained during the rewrite of the billing system, we were now able to ensure that the new time estimates were accurate.

The remaining systems and programs that need to be fixed are handled by running a "Pivot Test," which consists of a small sub-routine within each program. The pivot test checks the two digit date (year), if it is between 00 and 50 it will be assigned the 2000 prefix 20XX, if it is between 51 and 99 it will be assigned the 1900 prefix 19XX. We have already thoroughly tested the Pivot Test Routine,it isn't very elegant but it is quick and it will work.

The final time estimate to correct all of the existing systems is 12 weeks for 3 programmers. This is "worst case" leaving ample time for testing. Since we expect to be on the new Orcom system by the summer of 1999, we will not allocate any additional programmer time to Y2000 program updates on the remaining systems unless the Orcom installation timeline slips significantly.

Desktop Applications and Software Golden Valley standardized on Microsoft Windows NT Server 4.0, Microsoft Windows NT Workstation 4.0 and Microsoft Office 97. Most of the Microsoft products have varying degrees of Y2000 compliance and will be continually reviewed and updated as needed. Microsoft?s Y2000 Homepage address is:
http://www.microsoft.com/Year2000/


Windows NT Server 4.0
- Does not recognize 2000 as a leap year.
- Control Panel/Time Applet date may jump ahead an extra day. System date stays correct, displayed date is wrong.
- Custom Date properties in Office files are assumed to be 1900, if a two digit date is used.
- Using Find to locate a file created after 1999 will place give you a non-numeric date field.
- The following will fix the problems (all must be installed): 1. Service Pack 3
2. Microsoft Site Server Express 3.0 (Beta)
3. Windows NT Y2000 QFE Fixes.

SQL Server 6.5
- EXPIREDATE function does not properly handle dates greater then or equal to 2000. Possible overwrites of backup media may occur.
- Does not recognize 2000 as a leap year.
- Task Manager user interface also does not recognize 2000 as a leap year.
- Service pack 5 will address these problems.

SMS 1.2
- When clock rolls over to 2000, it resets to 1980.
- Year 2000 not recognized as a leap year.
- Service pack 3 fixes these problems.

Windows NT Workstation
- Same as Server, including fixes minus the Microsoft Site Server.

Access 2.0
- May misrepresent two digit dates as 1900?s instead of 2000.

Access 97
- May misrepresent two digit dates. 1/1/00 ? 12/31/29 as year 2000-2029 and 1/1/30 ? 12/31/99 as 1930-1999.

Excel 97
- Two digit dates may be misrepresented.
- Misrepresentation may cause miscalculations if dates are linked with other functions.

PowerPoint 97
- Saving to non-native (including PP4.0) may cause loss or incorrect entry of century data for Insert Date and Time functionality.
- A patch exists to fix this: PP7TRANS.DLL

Word 97
- Assumes any two digit date falls between 1930 and 2029.

Windows 95
- Windows file manager does not display dates beyond 2000.
- Command.com returns "Invalid Date" for any date from 00-79.

Visual Basic
- Y2000 Compliant up to 2030.

IE4.0
- Two digit dates may be misrepresented. This could cause improper cookie expiration dates, improper caching of web pages, and if "Web Wallet" is installed, not allow credit card expiration dates past 2000, or editing of balances.

Autocad/Softdesk
- Y2000 Compliant.

McAfee Antivirus
- Y2000 compliant.

Meeting Maker
- Y2000 Compliant up to 12/31/2039.

Netscape
- Y2000 compliant.

Norton Utilities
- Y2000 compliant.

Item 4: Actions remaining for corporate hardware to be Y2000 compliant.

IBM AS/400 & Digital VAX Computer Systems The hardware platform selected for the Orcom Systems? Utility Software Package is the RISC based IBM AS/400 computer system. Each of which is running IBM?s Y2000 compliant OS/400 operating system (V4R1 & V4R2).

The existing production (VAX 4000-600) and development (Micro VAX 3100-90) computer systems, and all of the on-line peripherals from Digital Equipment Corporation, are Y2000 compliant. Both machines are currently running version 6.2 of the VMS operating system, which again, is Y2000 compliant.
Desktop Computers and Servers With the need to replace the aging desktop computers within the corporation, Golden Valley elected to go with a common-desktop-computing-environment, selecting Gateway2000 computers as the standard desktop computer. All of the Gateway2000?s are equipped with Intel Pentium Pro processors and are Y2000 compliant.

In support of the common desktop, Dell PowerEdge 6100, Dell PowerEdge 4200 and Digital Alpha XL300 servers were selected. The PowerEdge 6100 and 4200 servers are Y2000 compliant (using Bios versions A05 and A01 respectively). Digital?s Alpha XL300 servers are also Y2000 compliant.
Item 5: Actions remaining for corporate facilities to be Y2000 compliant. GVEA facilities will be addressed in another section.
Item 6: Actions remaining for corporate infrastructure to be Y2000 compliant. GVEA infrastructure will be addressed in another section.
Item 7: Actions taken to identify and test embedded chips within corporate infrastructure. Embedded chips refer to computer chips that are "hard-wired" into a computer or system. Within the chip is a "burned-in" program that contains specific instruction sets. Chips containing these instruction sets can not be altered by software, they must be physically replaced with updated chips. All of the hardware covered in Item 4, per manufacture statements of Y2000 compliance, will not be affected by embedded chips.
Item 8: How will already identified Y2000 problems affect the services we provide. In the area of Corporate Computing we are in very good shape. Our biggest concern would be with the existing COBOL programs which, left unchecked, could have had disastrous affects on our General Ledger, Billing and Work Order Systems. All of these systems are being completely replaced with Y2000 compliant systems, there will be no adverse affects to the services we provide to our members.

The remaining Desktop Applications will provide very little disruption, if at all. Any adverse affects should be confined to internal efficiencies and will have no adverse affects on the services we provide to our members.
Item 9: Summary of necessary resources anticipated to remedy our corporate Y2000 issues. The final time estimate to correct all of the existing systems is 12 weeks for 3 programmers. This is "worst case" leaving ample time for testing. Since we expect to be on the new Orcom system by the summer of 1999, we will not allocate any additional programmer time to Y2000 program updates on these remaining systems unless the Orcom installation timeline slips significantly.

For all additional Corporate Computing systems we expect no more than 2 weeks for 2 employees to complete all necessary system testing. Again this is "worst case."
Item 10: Facilities and equipment certified by vendors as Y2000 compliant. - Orcom Systems, Inc., has provided written Y2000 certification for their entire software package.
- To date, all other hardware and software "certification" has come via vendor web pages, which have been printed out and are on file. We are continuing to pursue written certification from vendors where possible.
Item 11: Comments or advice that may be helpful in addressing this issue. We have tried to completely review every system and application within the area of Corporate Computing, however, the only real proof comes from direct testing. We recommend that all systems be put through the physical date change. Where possible we have used hardware and software in our "test environment," which we feel is sufficient for date testing, without causing disruption to production systems.
Item 12: Are new purchases required in order for your company to be Y2000 compliant? No. We have already made several major purchases during the last 12 months to update the functionality and speed of our existing Corporate Computing environment. All purchases were Y2000 compliant.
Item 13: Are you working with any trade organization for Y2000 compliance assistance? No. We have no plans to deal with any outside organizations on Y2000 compliance for our Corporate Computing environment.
SECTION 2: CORPORATE & OPERATIONAL COMMUNICATIONS

Team Leader

Jeff Yauney
phone: (907) 458-5778
e-mail: jpyauney@gvea.com
fax: (907) 451-5650


Introduction

This section outlines the time-line and tasks necessary to assure Y2000 compliance for all aspects of Golden Valley?s Corporate/Operational Communications. GVEA?s Communications environment consists of the following systems: 1) ATM Data Communications Network. 2) NEC Telephone Switch. 3) Rolm Telephone Switch. 4) Motorola 800MHz Trunked Radio 5) Analog Microwave System.

All systems will be certified by June 1999. Certification will be achieved using one or more of the following methods:
- Obtain certification from suppliers for compliant products
- Perform remedial action on systems with known non-compliance
- Perform extensive testing using actual data/time rollover on modified systems.
Item 2: Year 2000 planning cycle status for Corporate Computing

*Launch
*Inventory
*Assessment
*Repair
*Testing
*Finished
Completed.
Completed.
In progress, with some systems already completed.
In progress, with some systems already completed.
In progress, with some systems already completed.
In progress, with some systems already completed.

Item 3: Actions remaining for communications software to be Y2000 compliant. ATM Data Communications Network

Golden Valley has installed a corporate wide network with an Asynchronous Transfer Mode (ATM) backbone, providing either 155/622Mb ATM or 10/100Mb switched Ethernet to the desktop. All of the network electronics are from Cisco Systems, Inc., and consists of the following equipment:

- LightStream 1010 ATM Switch ? IOS Version 11.2
- Catalyst 5000 Series Switch ? IOS Version 3.1
- Catalyst 2820 Series Switches ? Version 7.02
- Catalyst 1900 Series Switches ? Version 7.02
- PIX Firewall ? Version
- AS5200 Universal Access Servers ? Version 11.2
- 4000 Series Router ? Version 11.2
- 2500 Series Routers ? Version 11.1 & 11.2

All of the data network electronics in use at Golden Valley come from Cisco Systems, Inc. Cisco has stated (via their web page) that each device listed above, and its? corresponding software to be Y2000 compliant. Cisco?s Y2000 homepage address is:
http://www.cisco.com/warp/public/752/2000/.
NEC Telephone Switch
The NEC telephone switch is used solely as a backup switch for the Dispatch Center. This provides GVEA with a fail-over system and allows for uninterrupted phone service in case of outage or when the ROLM telephone switch is being serviced. All related software for the NEC switch is currently under review. To date we have found no Y2000 problems.
ROLM Telephone Switch
We have reviewed the ROLM 9751 switch and found that it will require a software patch to be Y2000 compliant. We have been informed that the Y2000 patch is now available and we are waiting for delivery.
Motorola 800MHz Trunked Radio.
We have reviewed the Motorola Y2000 "Hot-Line" and found that the following systems are Y2000 compliant:

Trunking Central Controller ? AMSS ? Primary Control System at the central site.
Startsite Controllers ? AMSS ? Primary Control System at the remote sites.
Centracom II ? Consoles at the central site.

The following system is not Y2000 compliant:

SIMS II ? Stand alone system log, this is not essential equipment and the system can operate without it being on-line. There is a Y2000 software patch that we have ordered.
Microwave System
Within the GVEA operational communications network, analog microwave units interconnect all substations to the central facility. In addition, GVEA?s microwave system interconnects with the State of Alaska?s Division of Communications microwave system providing interconnectivity with utilities in the south. The analog system is from Motorola and has no embedded chips within the system that will be affected by the Y2000 date problem.

The connections with the State of Alaska are currently being reviewed, and Y2000 preparedness is unknown at this time.

Item 4: Actions remaining for corporate hardware to be Y2000 compliant. All of the hardware in use within our corporate & operational communications environment is Y2000 compliant, per manufacturer/vendor statements of compliance. We are in the process of conducting a full review on our connectivity with the State of Alaska. Since the State is an outside agency we will be requesting assurance of Y2000 compliance directly from them.
Item 5: Actions remaining for corporate facilities to be Y2000 compliant. GVEA facilities will be addressed in another section.
Item 6: Actions remaining for infrastructure to be Y2000 compliant.
N/A
Item 7: Actions taken to identify and test embedded chips within corporate infrastructure.
Embedded chips refer to computer chips that are "hard-wired" into a computer or system. Within the chip is a "burned-in" program that contains specific instruction sets. Chips containing these instruction sets can not be altered by software, they must be physically replaced with updated chips. All of the hardware covered in Item 3, per manufacture statements of Y2000 compliance, will not be affected by embedded chips.
Item 8: How will already identified Y2000 problems affect the services we provide.
In the area of Corporate Communications we are in very good shape. Our biggest concern is our connectivity to the south via the State of Alaska. is the successful installation of the Y2000 software patches on the telephone switches. These patches appear to be straight forward and should prove to be of little impact to our corporate communications network. There will be no adverse affects to the services we provide to our members.
Item 9: Summary of necessary resources anticipated to remedy our corporate Y2000 issues.
For Corporate Communications we expect no more than 1 week for 2 employees to complete all necessary system testing.
Item 10: Facilities and equipment certified by vendors as Y2000 compliant. To date, all other hardware and software "certification" has come via vendor web pages, which have been printed out and are on file. We are continuing to pursue written certification from vendors where possible.
Item 11: Comments or advice that may be helpful in addressing this issue. We have tried to completely review every system and application within the area of Corporate Communications, however, the only real proof comes from direct testing. We recommend that all systems be put through the physical date change. Where possible we have used hardware and software in our "test environment," which we feel is sufficient for date testing, without causing disruption to production systems.
Item 12: Are new purchases required in order for your company to be Y2000 compliant? Several of the software patches for the telephone systems may have to be purchased. We are reviewing our maintenance agreements with the vendors to determine if the patches will be covered under our existing agreements.
Item 13: Are you working with any trade organization for Y2000 compliance assistance? No. We have no plans to deal with any outside organizations on Y2000 compliance for our Corporate Communications environment


SECTION 3: SCADA OPERATIONS AND SECURITY

Team Leader

Fred LeBeau
phone: (907) 451-5640
e-mail: falebeau@gvea.com
fax: (907) 451-0556


Item 2: Project status

*Launch
*Inventory
*Assessment
*Repair
*Testing
*Finished
Completed.
Completed.
Completed.
In progress.
In progress.
Pending.

Item 3: Actions remaining for software
1. Continue and complete date/time rollover testing for SCADA/EMS
2. Replace energy recorder translation software with compliant version from vendor
3. Replace Procomm Plus Script for Protective Relay Access with compliant software from vendor
4. Continue with procurement of replacement SCADA/EMS
Item 4: Actions remaining for hardware
No known non-compliance in any computer hardware
Item 6: Actions remaining for Infrastructure Communication Equipment to be handled by Computer and Network Services
Item 7: Actions remaining for embedded systems 1) RTU(s) will be tested during actual date/time rollover testing of SCADA/EMS
2) GPS Time and Frequency Source fully certified by manufacturer
Item 8: Problems found and affect on services provided Digital Equipment issued a patch for the VMS operating system used on the SCADA/EMS computers. The problems fixed by this patch could have resulted in the failure of the operating system or an application thus significantly reducing the availability of the SCADA/EMS.

Problems have been found in the SCADA/EMS software anywhere a date was modified using addition, subtraction, division, or multiplication. This could have affected the execution of interchange schedules and Automatic Generation Control creating problems with energy transactions and regulation of frequency.

The translation software for reading energy recorders was flawed in several ways. This could have affected our ability to accomplish the timely and accurate processing of bills for purchases and sales of bulk power.
Item 9: Resources necessary to remedy Services agreement with Landis & Gyr for the SCADA/EMS software and hardware
Digital Equipment for VAX hardware and VMS operating system software
Myself at about 20% for remainder of 1998
CNS for miscellaneous minor items concerning PC applications
Item 10: Facilities and Equipment certified by vendors 1) Service contract for SCADA/EMS includes a warranty good until 2001
2) GPS Time and Frequency source fully certified by vendor
3) Replacement energy recorder translation software certified by manufacturer
4) SCADA/EMS computers certified by Digital Equipment
Item 11: New purchases 1) Energy Recorder translation software
2) Protective Relay Interrogation software
Item 12: Cooperation with Trade Organizations 1) GVEA is working with ASCC.


SECTION 4: PIPELINE OPERATIONS

Team Leader

Alex Gajdos
phone: (907) 451-5659
e-mail: asgajdos@gvea.com
fax: (907) 451-5682


Question 2: Project Status
*Launch
*Inventory
*Assessment
*Repair
*Testing
*Finished
Completed.
Completed.
Completed.
In progress waiting on final from vendor.
Pending.
Pending.

Question 3: Software The Leak Detection System (LDS), PLC ladder logic upgrades, and installation are scheduled to be completed by September 1998. The vendor is currently on schedule. MMI system will be modified by September 1998 through a Y2k compliant "factory suites" upgrade.
Question 4: Hardware There are no hardware upgrades required.
Question 5: Pipeline Facilities
See question number 3.
Question 6: Infrastructure
See question number 3.
Question 7: Embedded chips testing
Testing will occur during software modifications. There are no firmware or embedded chip problems.
Question 8: Specific Problems
Ladder logic in PLC?s need to be modified. MMI software and systems need to be modified.

Question 9: Resources

K&C Associates (907) 455-6472.
Question 10: Vendor Certification
All pipeline facilities.
Question 11: Comments
We expect to be fully tested and compliant in the third quarter of 1998.
Question 12: New Purchases Yes, LDS ladder logic upgrade

Question 13: Trade Organizations

No

SECTION 5: FAIRBANKS AREA GENERATION PLANTS

Team Leader

Alex Gajdos
phone: (907) 451-5659
e-mail: asgajdos@gvea.com
fax: (907) 451-5682


Question 2: Project Status
*Launch
*Inventory
*Assessment
*Repair
*Testing
*Finished
Completed.
Completed.
Completed.
In progress waiting on final from vendor.
Pending.
Pending.

Question 3: Software Gas turbine control systems and PLC ladder logic upgrades are scheduled to be completed and installed by September 1998. The MMI system is scheduled for upgrade at the same time. Testing will occur prior to installation.
Question 4: Hardware
There are no hardware upgrades required.
Question 5: Facilities
See Question 3.
Question 6: Infrastructure
See question 4.
Question 7: Embedded chips Testing will occur prior to system installations scheduled for September 1998. There are no known embedded chip problems at this time.
Question 8: Specific Problems
Ladder logic in PLC?s need to be modified. MMI software and systems need to be modified. Unit controllers need to be modified or microprocessors upgraded.
Question 9: Resources
ICS, Inc. (518) 383-8078.
Question 10: Vendor Certification
Wonderware is certified Y2000 compliant. ICS controllers with 486 microprocessors are Y2000 compliant.
Question 11: Comments
We expect to be fully tested and compliant in the third quarter of 1998.
Question 12: New Purchases
Upgrades to gas turbine control system, MMI and ladder logic.
Question 13: Trade Organizations
No


SECTION 6: HEALY GENERATION PLANT

Team Leader

Name: Frank Abegg
Phone: (907) 451-5659
e-mail: fabegg@gvea.com
Fax: (907) 451-5682


Item 2: Year 2000 planning cycle status for Healy Generating Plant

*Launch
*Inventory
*Assessment
*Repair
*Testing
*Finished
Begun.
In Progress.
Pending.
Pending.
Pending.
Pending.

Items 3 through 13: The Healy Plant, along with the Healy Clean Coal Project (HCCP) has been under construction for some time. Many of the critical systems at the Healy Plant are being upgraded as the HCCP is being constructed. GVEA is confident that the utilization of state-of-the-art equipment at the Healy facilities minimizes the risk of such systems being Year 2000 noncompliant.

Although the Year 2000 efforts in this identified area have not undergone the level of review that the other areas have, GVEA expects that this area will achieve the milestones desired by GVEA management for this Year 2000 process. Considerable coordination will be required between GVEA and the Alaska Industrial Development and Export Authority to accomplish this task. The work has commenced.


SECTION 7: TRANSMISSION AND DISTRIBUTION FACILITIES

Team Leader

Tim DeVries
phone: (907) 451-5669
e-mail: trdevries@gvea.com
fax: (907) 451-5638


Introduction This section outlines the time-line and tasks necessary to assure Y2000 compliance for all aspects of Golden Valley?s Transmission and Distribution Facilities. GVEA?s Transmission and Distribution Facilities consists of the following equipment: substation circuit breakers, transformers, regulators, tap changer controls, relays, meters, GPS clocks, DSM?s, switchgear, reclosers, recloser controls and test equipment.
Item 2: Year 2000 planning cycle status for Transmission and Distribution Facilities:
*Launch
*Inventory
*Assessment
*Repair
*Testing
*Finished
Completed.
Completed.
Partially complete, awaiting vendor response
Pending assessment.
Pending.
Pending.

Item 3: Actions remaining for Transmission and Distribution Facilities software:
Waiting for vendor response.
Item 4: Actions remaining for Transmission and Distribution Facilities computer hardware to be Y2000 compliant:
Waiting for vendor response.
Item 5: Actions remaining for Transmission and Distribution Facilities to be Y2000 compliant:
See item 4.
Item 6: Actions remaining for Transmission and Distribution Facilities infrastructure to be Y2000 compliant:
See item 4.
Item 7: Actions taken to identify and test embedded Transmission and Distribution Facilities infrastructure:
Embedded chips refer to computer chips that are "hard-wired" into a computer or system. Within the chip is a "burned-in" program that contains specific instruction sets. Chips containing these instruction sets can not be altered by software, they must be physically replaced with updated chips. See item 4.
Item 8: How will already identified Y2000 problems affect the services we provide:
To date no problems have been identified.
Item 9: Summary of necessary resources anticipated to remedy our corporate Y2000 issues:
If necessary, the resources will be vendors. See item 4.
Item 10: Facilities and equipment certified by vendors as Y2000 compliant:
See item 4.
Item 11: Comments or advice that may be helpful in addressing this issue:
We expect to be compliant in the third quarter of 1998.
Item 12: Are new purchases required in order for your company to be Y2000 compliant?
At this time no purchases are anticipated.
Item 13: Are you working with any trade organization for Y2000 compliance assistance?
No.


SECTION 8: BUILDING FACILITIES AND FIRE PROTECTION

Team Leader

Tom Hartnell
phone: (907) 451-5663
e-mail: tkhartnell@gvea.com
fax: (907) 451-5681

Introduction
This section outlines the time-line and tasks necessary to assure Y2000 compliance for all aspects of Golden Valley?s Facilities and Fire Systems. GVEA?s Facilities and Fire Systems environment consists of the following systems: 1) Honeywell EXCELL 100 HVAC controller, 2) Simplex Fire System, Model 4020, 3) a variety of non-PLC fire systems, and 4) manual HVAC control systems.

The two Y2000 impacted systems are currently certified by the manufacturers. Certification has been achieved by:
Obtaining certification from suppliers for the Simplex Fire System.
Obtaining certification from the manufacturer, Honeywell, for the Excell 100 HVAC control system.
Item 2: Year 2000 planning cycle status for Corporate Facilities and Fire Systems:
*Launch
*Inventory
*Assessment
*Repair
*Testing
*Finished
Completed.
Completed.
Completed.
Completed.
Completed.
Completed.

Item 3: Actions remaining for Corporate Facilities and Fire Systems software:
Nothing further required.
Item 4: Actions remaining for Corporate Facilities and Fire Systems software hardware to be Y2000 compliant:
Nothing further required.
Item 5: Actions remaining for corporate Facilities and Fire Systems to be Y2000 compliant:
Nothing further required.
Item 6: Actions remaining for Corporate Facilities and Fire Systems infrastructure to be Y2000 compliant:
Nothing further required.
Item 7: Actions taken to identify and test embedded chips within Corporate Facilities and Fire Systems infrastructure:
Embedded chips refer to computer chips that are "hard-wired" into a computer or system. Within the chip is a "burned-in" program that contains specific instruction sets. Chips containing these instruction sets can not be altered by software, they must be physically replaced with updated chips.

The Simplex Fire System has been upgraded by the supplier.

The Honeywell Excell 100 HVAC system was certified by the manufacturer prior to installation.
Item 8: How will already identified Y2000 problems affect the services we provide:
Not applicable.
Item 9: Summary of necessary resources anticipated to remedy our corporate Y2000 issues:
Not applicable.
Item 10: Facilities and equipment certified by vendors as Y2000 compliant:
The Simplex Fire System has been certified by the supplier.

The Honeywell Excell 100 HVAC system was certified by the manufacturer prior to installation.

Item 11: Comments or advice that may be helpful in addressing this issue:

The Simplex and Honeywell systems have been tested by the respective vendor technicians.
Item 12: Are new purchases required in order for your company to be Y2000 compliant?
No purchases are required.
Item 13: Are you working with any trade organization for Y2000 compliance assistance?
No. We have no plans to deal with any outside organizations on Y2000 compliance for our Corporate Facilities and Fire Systems environment